Making Washington Terrace City a Better Place, One Construction Project at a Time.
6/15-20/26, Chip Seal Road Maintenance
Chip seal maintenance will be performed on two working days. On day one the road will be chip sealed, then three days later a fog seal coat will be applied. The roads will be closed to through traffic during periods of active work, but will be open during the intervening days. Please see the attached map for more information. Dates for roadway sections are also listed below.
300 E: June 15 & 18, 2026
4400 S: June 15 & 18, 2026
4700 S: June 16 & 19, 2026
4800 S: June 16 & 19, 2026
4900 S: June 17 & 20, 2026
5100 S: June 17 & 20, 2026
5350 S: June 17 & 20, 2026
2026 Road Maintenance
2026 Annual Street Maintenance Projects
Washington Terrace City has several street maintenance projects planned for this summer. Routine street maintenance involves proactive preservation methods to preserve and prolong the Remaining Service Life (RSL) of the streets. Each street has been analyzed and prioritized for what type of treatment and when it needs to be treated. Applying the right treatment at the right time will increase the RSL.
These asphalt preservation treatments will consist of:
- Chip Seal
- Slurry seal
- Asphalt overlay
- Soft Spot repairs
These projects are scheduled to occur between June 15th and August 31st, 2026. Residents and businesses within the area will be notified by door flyer prior to construction in their area. Please be vigilant in the construction zones and obey traffic control signs to help ensure workers’ safety.
The street maintenance applications typically take 1-2 days to apply. Residents in the area will be notified prior to construction and there will be no parking allowed on the street during the construction. Not having to work around parked vehicles and obstacles in the street will ensure a quality project and safety for the construction crew and personal property.
2026 Washington Terrace Construction Projects
Street maintenance and infrastructure development is a little like being conscious during surgery; although the process may be uncomfortable, the end result brings relief and improvement in quality of life.
City staff meticulously prioritize annual street maintenance initiatives and infrastructure enhancements to ensure the ongoing preservation of the city's assets.
Several projects are currently in the planning phase for summer 2025. This year’s initiatives include:
- Sealing and resurfacing of street cracks
- Enhancements to the sidewalks at the north entrance of Rohmer Park, located at 5100 S. 600 W.
- Enhancements to the sidewalks at the north entrance of Rohmer Park, located at 5100 S. 600 W.
- Sewer pipelining on 500 west between 4800 S. and 4400 S.
Before the commencement of each project, a detailed map indicating the location and project timeline will be made available on the city website, along with updates on the project's status throughout the construction phase.